Thursday, 17 January 2013

November 2012

In the past few months progress has been slow. Last November the suspended slab was formed up, then we ran the pipework for the floor heating in the games room, a few very stressful days and late nights working by spotlight to prepare for the concrete to be poured. Definitely a few grey hairs for us both that day!!


The concrete getting pumped up to the suspended slab....


Games room floor getting poured......


No comments:

Post a Comment